How It Works2018-07-14T10:20:58+00:00

How it works

When forming structural openings, our temporary works focus on propping and needling. When undertaking this element of works we:

  • Secure the site and ensure safe access (may involve installing some temporary works)Understand how the structure works by researching existing
  • Information and carrying out on-site surveys
  • Identify the need for temporary works and associated risks
  • Obtain consent from owners of neighbouring structures that may be affected
  • Provide competent persons to carry out the design and design checking (permanent and temporary works)
  • Make safe the existing structure (may involve installing some temporary works) in preparation for the main works
  • Trained Specialists carry out demolition/refurbishment and rebuild in an agreed sequence (may involve installing further temporary works) and control the works by using a permit-to-load system
  • Review and manage on-site alterations and changes
  • Insert permanent works such as –  concrete Pad-stones, concrete lintels and steel beams and columns
  • Make good and secure all masonry above the inserted permanent works
  • Remove any temporary works in an agreed sequence so load is transferred to the permanent works and control the works by using a permit-to-remove system

“The Tranco supervisors were very informed and we had daily site tours looking at the planned works and the issues raised”

Barrie Balaam , Site Manager, Eric Wright Special Projects